Machine X and Y work at their respective constant rates - DS

by Guest Sat Aug 16, 2008 9:04 pm

My date is on Wednesday. I would like to ask if someone can explain the answer.

Machine X and Y work at their respective constant rates. How many more hours does it take Machine Y, working alone, to fill a production order of a certain size than it takes Machine X, working alone?

1. Machine X and Y, working together, fill a production order of this size in two thirds the time that Machine X does.
2. Machine Y, working alone, fills a production order of this size in twice the time that Machine X, working alone, does.

OA is E. I get y=2x from the two statements. Therefore, Machine Y hours will be doube the Machine X hours. So why is the answer E?

Thank you.
abovethehead
 
 

by abovethehead Tue Aug 19, 2008 12:39 pm

Let x and y represent the respective rates of X and Y.
We must know the values of both x and y to know "how many more hours". In other words, y = 2x does not tell us how many more hours the job takes Y than X, only that Y takes twice as long. If x = 2, y = 4 and the difference is 2. However, if x = 3, y = 6, and it now takes 3 hours longer.

1) 1/x + 1/y = 1/T
So, T (total time) = xy / (x+y)
Statement 1 tells us that the total time or combined = 2/3 x
So, xy / (x+y) = 2/3 x
Solve and you get y = 2x
INSUFFICIENT - again, it only gives us a relationship

2) translated gives y = 2x

Statements 1 and 2 provide the same information, so either D or E
Since we cannot combine 2 similar equations to solve for 2 variables, the answer is E
Guest
 
 

by Guest Tue Aug 19, 2008 1:07 pm

Got it. Thank you.
fangming_li
Forum Guests
 
Posts: 2
Joined: Fri Jun 11, 2010 5:27 am
 

Re: Machine X and Y work at their respective constant rates - DS

by fangming_li Fri Jun 11, 2010 12:29 pm

"Let x and y represent the respective rates of X and Y.
1) 1/x + 1/y = 1/T
So, T (total time) = xy / (x+y) "


x and y should not be letted as rates of X and Y. It should be
time.
mschwrtz
ManhattanGMAT Staff
 
Posts: 498
Joined: Tue Dec 14, 2004 1:03 pm
 

Re: Machine X and Y work at their respective constant rates - DS

by mschwrtz Mon Jul 12, 2010 11:10 pm

That right. I assume that that was just a slip of the keyboard, abovethehead, since you treated the variables as representing times throughout your explanation.
sudaif
Course Students
 
Posts: 125
Joined: Fri Jun 05, 2009 7:46 am
 

Re: Machine X and Y work at their respective constant rates - DS

by sudaif Sun Jul 25, 2010 2:58 pm

thanks for pointing out the m. he had me confused for a second!
RonPurewal
Students
 
Posts: 19744
Joined: Tue Aug 14, 2007 8:23 am
 

Re: Machine X and Y work at their respective constant rates - DS

by RonPurewal Thu Aug 05, 2010 7:32 am

glad it helped
raviteja.pandiri
Forum Guests
 
Posts: 1
Joined: Sat Sep 18, 2010 5:08 pm
 

Re: Machine X and Y work at their respective constant rates - DS

by raviteja.pandiri Sun Sep 19, 2010 12:11 am

But we are having a definite quantity "X"..Right?So I still feel the answer is D.

Because there is no other value/variable affecting the outcome except for the "X".Please clarify if I am going badly wrong somewhere!
tim
Course Students
 
Posts: 5665
Joined: Tue Sep 11, 2007 9:08 am
Location: Southwest Airlines, seat 21C
 

Re: Machine X and Y work at their respective constant rates - DS

by tim Sat Sep 25, 2010 6:56 am

um, X is not a definite quantity. definite quantities are specific numbers, not variables, not ranges of numbers, not even choices between two numbers. if you get an answer of X, that means you don't know for sure what the answer is since X can mean many things..
Tim Sanders
Manhattan GMAT Instructor

Follow this link for some important tips to get the most out of your forum experience: